RemBind® Feature Project

PFAS Soil Stabilisation at Military Base

Stakeholders

Federal, Government, Land Owner, Community, Authority

Location

North Dakota, USA

Contaminant Type(s)

PFAS (PFOS, PFOA, PFOSA, multiple compounds)

Product(s) Used

RemBind 100

Leachability Reduction Achieved

PFAS: >99% over 19 month monitoring period

Equipment Used

Excavator

Project Type

PFAS Soil Stabilisation at Military Base

Project Summary

RemBind delivered in-situ PFAS stabilisation at a military base fire training facility, addressing legacy AFFF contamination built up over decades of firefighting foam exercises. Concentrations at the site were high, so a field proven treatment technology was implemented with protocols refined through bench-scale testing before being applied systematically across the site.

Project Outcomes

  • Successfully treated PFAS contamination from legacy AFFF fire training activities at an active military base.

  • Treatment was done on site, so there was no need to excavate soil and truck it off base, and base operations continued without disruption.

  • PFAS immobilisation has held steady through 19 months of monitoring at the facility.

  • The field data gives a validated basis for rolling the technology out to other military bases.

  • Treatment integrity was confirmed with moisture and NMR monitoring, even under live operational conditions.

  • The project establishes a protocol Defence can apply at other fire training facilities nationally.

Proven at Scale

RemBind provides commercially proven remediation solutions at full project scale, delivering consistent performance across complex and high-risk contamination challenges globally.